Risk management systems

  • What Software Systems are currently used by the Council (please identify each system if more than one is used) for:

* Programme and / or Project management? Microsoft Project
* Risk Management recording and reporting JCAD Risk Module

  • When do the contracts expire for each software system used? MS Project 30 Nov 2024

For JCAD - Annual renewal in December each year

  • do you have any planned changes or upgrades of the software currently used? If so, when? No None currently planned for JCAD risk module
  • if you do not have a system how are programmes and projects managed currently? n/a n/a
  • Who is the person responsible for the identified Software Systems? Please provide full name, title and contact information if possible.
  • For MS Project- Technology Contracts Manager For JCAD Risk Module - Risk Manager

Our response